The WIP Schedule: The Report Your Bonding Company Reads Before Your P&L

If you run a construction company, your profit and loss statement (P&L) tells you very little until the year is almost over. Revenue gets recognized as work progresses, costs come in lumpy, and a job that looks fine in March can turn into a loss by August.

The report that actually tells you how you're doing is the work-in-progress (WIP) schedule. Your bonding company knows this. It's one of the first things a surety underwriter asks for, and it often carries more weight with them than your income statement.

Most contractors I talk to have a WIP schedule because their CPA builds one at year end. Very few use it monthly to run the business. That's the gap.

What the WIP schedule shows

One row per open job. For each job, you track:

That last column is where the story is.

A simple example

Say you have a $1.2M job with an estimated cost of $1.0M. That's a planned gross profit of $200K, about 17%.

You've spent $600K so far, so the job is 60% complete. That means you've earned $720K of revenue.

Scenario 1: You've billed $800K. You're overbilled by $80K. That's not extra profit. It's cash you've collected for work you haven't done yet. On the balance sheet it's a liability. If you spend that cash on overhead or a new truck, you're borrowing from the end of the job. When the last 40% of the work comes due, the money to pay for it is already gone.

Scenario 2: You've billed $600K. You're underbilled by $120K. Sometimes that's just a billing lag, and you need to get the pay app out. But underbillings are also where cost overruns hide. If you've spent more than planned, percent complete runs ahead of reality and the job looks further along than it is. Sureties know this, which is why many of them discount or question large underbillings.

Neither number is automatically good or bad. But both need an explanation every month.

Watch for margin fade

The most useful thing a monthly WIP schedule gives you is margin fade: the difference between the gross profit you bid and the gross profit you're now projecting.

A job bid at 17% that's now projecting 11% has faded six points. If you catch that at 30% complete, you can still do something about it: push change orders, look at crew productivity, renegotiate with a supplier. If you catch it at 95% complete, all you can do is take the loss.

When fade shows up across several jobs, it usually points to something bigger. Maybe your estimating is off, a project manager (PM) is struggling, or your labor rates have gone up faster than your bids.

The hard part is the estimate to complete

A WIP schedule is only as good as the estimated cost to finish each job. If that number is stale, every other column is wrong.

This is where most contractors struggle. Updating the estimate takes a real conversation with each project manager every month: What's left? What's changed? What do you know that isn't in the system yet? It's not an accounting exercise. It's an operations conversation that happens to produce accounting numbers.

Why this matters beyond the surety

A good monthly WIP process does three things for you:

  1. Protects your bonding capacity. Sureties reward contractors who show clean, consistent WIP reporting with fewer surprises at year end.
  2. Protects your cash. You stop spending overbillings as if they were profit.
  3. Makes you a better estimator. Tracking fade job by job shows exactly where your bids are wrong.

Where to start

Take your open jobs and build the schedule for last month. Sit down with each PM and update the cost to complete. Then look at two things: which jobs are overbilled (and whether that cash is still in the bank), and which jobs have faded more than a few points since the bid.

If that exercise surprises you, it's worth making it a monthly habit. That's a core part of the CFO work I do with contractors at Laverton Advisory: a WIP schedule your PMs trust, your surety likes, and you can actually run the business from.


Derek Hammock is a CPA and fractional CFO at Laverton Advisory. He works with founder-led businesses to build the financial clarity they need to make better decisions.

Company examples in this post are illustrative scenarios, not specific clients, unless stated otherwise.